Section 3 – Pre Installation Information
Physical installation of the console is normally carried out by a specialised transportation company. In some
cases this will have been arranged by the local SSL office, in other cases by the facility.
The cables that run between console and processor can be shipped in advance of the console in a separate kit (the
pre-install kit). These cables should be installed by the facility engineers. Instructions for installing these cables
are found on pages 29 to 31 of this manual.
Note: Cables for the connection of ancillary functions, Meters, talkback, oscillator and any custom switches etc. are
not supplied by SSL and will need to be provided by the facility. See pages 43–45 for wiring information.
Before the console is installed all building work should be completed and the environment MUST be clean
otherwise the warranty will be rendered invalid.
Before commissioning can take place the following MUST be completed:
Air Conditioning installed, tested, blown-through and working
Lighting installed and tested
Cable Trunking installed
Wall and floor finishes completed
Power Distribution installed and tested
Cables installed and tested
Monitor loudspeakers installed and working
Other utilities (telephone, water etc.) available
Services provided by SSL
Commissioning
All C100 systems include on-site commissioning by an SSL engineer. This is usually expected to take from 2 to 4
days depending on system size, configuration and options. Large systems, or consoles split for shipment, may
require an additional 1–2 days of commissioning time.
You will be contacted by your local SSL office or agent shortly before delivery to arrange a commissioning date.
Training
Two days of standard operator training are provided with each C100 system. If required, this is scheduled to take
place immediately following the commissioning period and is usually carried out by the commissioning
engineer. A further day of advanced operator training is available at additional cost.
On-site maintenance training is also available at additional cost. This can be either one day for a basic overview
or two days for more advanced training.
Training should be requested at time of order. For all training, we recommend that no more than five persons
attend each session. If the use of an interpreter is necessary the training period may need to be extended (at
additional cost). Note that travel and subsistence costs are not normally included. Please contact SSL’s Training
Department at: support@solid-state-logic.com.
Warranty
All systems normally include 13 months warranty from date of shipment. This does not include consumable
items such as magnetic media, disks etc. Further details may be found in SSL’s Conditions of Trading (printed
on the reverse of all SSL invoices).