Appendix F – Stagebox Installation
Page 67
Appendix F: Additional Information for Installing Stageboxes
When positioning and installing C-SB the following rules must be followed:
• Unobstructed airflow at front and rear.
• No obstruction to airflow, horizontal or vertical, within 300mm in front, above and below both the front
and rear panels.
• Ambient temperature no more than 30˚C measured at the air intake (lower front opening) or just below the
rear heatsink.
• Microphone cables must not obstruct the air intake. To help ensure this, a cable guide is provided down
the sides of the rack.
Design Requirements for a Flightcase
If a Stagebox is to be installed into a flight case the following requirements, in addition to those above, must be
met to ensure adequate passive cooling – otherwise user must install a ‘forced-ventilation kit’.
• Both front and rear covers must be completely removed during operation.
• The front and rear covers must be deep enough to ensure that the front and rear faces of Stagebox are flush
with front and rear of the open flight case.