22 en | Hardware Installation RAID Subsystem DVA-08K | Installation Manual
F.01U.027.797 | V2 | 2008.08 Bosch Security Systems
3.3 General Installation Procedure
The following instructions can save installation time. Detailed, illustrated instructions for each
component are given in the following sections.
1. Unpack: Unpack the subsystem and confirm that all the components on the Unpacking
Checklist have been included.
2. Rack/Cabinet installation: If the subsystem is going to be installed in a rack or cabinet, it
should be installed prior to installing the hard drives. Installing the subsystem into a rack
or cabinet requires at least two (2) people.
3. Install drive trays: After the hard drives have been installed into the drive trays, the drive
trays must be installed into the enclosure itself. (See Section 3.6 Drive Tray Installation)
4. Cable connection: Use the power cords that came with the subsystem to connect the
subsystem to the main power source. Use self-purchased SCSI cable to connect host
ports to servers.
5. Power up: Once the components have been properly installed and all cables are properly
connected, you can power up the subsystem and configure the RAID array. (See
Section 5.4 Power On)
3.3.1 Installation Procedure Flowchart
Table 3.1 shows a flowchart of the installation procedure. As you complete each step, check
off the “Done” box on the right. Please use this flowchart in conjunction with the instructions
that follow.
3.4 Unpacking the Subsystem
Use the unpacking checklist in your package to check packing contents. Carefully check the
items contained in each box before proceeding with installation.
CAUTION!
To ensure that your system is correctly installed, please follow the steps outlined below. If you
follow these steps, installation will be fast and efficient. If you do not follow these steps, you
may have incorrectly installed the hardware.
Step Installation Procedure Done
1Unpack See Section 3.4 Unpacking the Subsystem
3 Rack/Cabinet Installation See Section 3.5 Rackmounting
5 Drive Tray Installation See Section 3.6 Drive Tray Installation
6 Cable Connection
7Power On See Section 5.4 Power On
Table 3.1 Installation Procedure Flowchart
NOTICE!
A detailed packing list can be found in your product shipping package or product CD.